"2008" Photograph archive
Last updated on  Wednesday, 20 August 2008  


Photographs taken between 12th & 18th August 2008
Taken by David Coleman
Uploaded on 20/08/2008

 

2234
Tuesday, 12.8.08. All ready for our visitors - as John Trott chats with Bob Winchurch on No. 7.

2237
Bob takes the controls as the first train heads up towards Corris.

2238
Member Richard Slate stops at Maespoeth to photograph and measure diesel locos 5 & 6 for modeller's drawings.

2239
John is all smiles as he machines axleboxes for Carriage No. 22.

2240
It is raining for much of the day...

2241
...which helps No. 7 leave a visible trail of steam behind it...

2242
...but it clears up later in the day!

2243
In the evening, the Aberystwyth gang appear and Stephanie soon acquires her usual tribal markings!

2244
Andrew and two Richard's dismantle a turnout...

2245
...while yours truly surveys the site...

2248
...which involves much climbing through hedges!

2255
Later on, the common crossing from the dismantled turnout is moved...

2257
...and loaded onto the bogie waggon for storage elsewhere.

2265
Thursday, 14.8.08. In the evening, dismantling of a further turnout commences, but the midges soon cause work to be abandoned!

2269
Friday, 15.8.08. Trefor adjusts the position of No. 7 so that he can change wicks in the lubricators of the die blocks...

2271
...while outside, Richard continues dismantling work on a turnout.

2339
Monday, 18.8.08. Roger Gray walks to No. 6 to move the train into the platform as Andrew passes No. 7, gently simmering on the middle road...

2340
...while the heritage stock awaits the train...

2341
...which will be moved after the brake test is complete.

   

Photographs taken between 5th & 10th August 2008
Taken by David Coleman
Uploaded on 11/08/2008

 

2177
Tuesday, 5.8.08. The sign board on the gantry has been changed already!

2178
Birthday boy cleans up for his party after driving No. 7 all day!

2181
In the evening, Trefor arrives to give more TLC to No. 7...

2182
...by cleaning up the slippers on the slide bars.

2183
Thursday, 7.8.08. Same scene two days later - has Trefor been home?

2184
Richard Shipman takes a break from cleaning out the fire.

2219
Sunday, 10.8.08. Malcolm removes couplings...

2220
...and Bob prepares the fire...

2221
...after an exceedingly wet Saturday - it persisted down all day!

2223
Later in the day, Nick Haslam and Bob chat between trains...

2224
...while Richard (and Bryn) are changing sleepers...

2225
...duly photographed by our visitors.

2226
In the evening, Bryn, Chris, Bill and Richard try out some 7.25" rolling stock...

2231
...and Chris gets so excited, Bill has to hold her still to stop derailments...

2232
...but there is no holding her back!


Photographs taken on 2nd & 3rd August 2008
Taken by Alf Oxford
Uploaded on 04/08/2008

 

0001
Excited passengers, with bears, join the train...

0002
...which had been appropriately decked out.

0003
The honorary stationmaster for the weekend greeted the passengers.

0005
Another train arrives back at Corris.

0006
Paul Bailey prepares to drive to Maespoeth.

 

Photographs taken between 28th July & 3rd August 2008
Taken by David Coleman
Uploaded on 04/08/2008

 

2066
Monday, 28.7.08. John Trott shows a group of passengers the inside of the Carriage Shed as...

2067
...fireman Roger Gray debunks from the cab of No. 7 to take on water!

2068
No. 7 basks in the midday sun at Corris.

2070
At the end of the day, Roger drives No. 7 back to Maespoeth.

2071
Tuesday 29.7.08. In the evening, Trefor arrives to give No. 7 a little TLC after its day's work...

2072
...by fitting new wicks in the lubricators.

2089
Wednesday, 30.7.08. Purely by accident while at work, an over-size steam train was spotted near Llandanwg!

2104
Thursday, 31.7.08. Glyn arrives at Maespoeth to prepare the ground for a lad's (and lasses!) weekend...

2105
...by levelling the trackbed to extend the future loop.

2107
In the evening, Trefor arrives to clean No. 7 and prepare it for the weekend...

2109
...by packing the slippers on the slide bars.

2110
Outside it is raining heavily...

2112
...and everybody shelters inside with a cuppa...

2113
...and then provides one for Richard Evans, who...
 

2114
...is digging a trench for the platform edge wall.

2118
Friday, 1.8.08. Andrew shovels concrete out of the dumper - but why not tip it?

2120
By evening, stone ballast has been delivered and some sleepers are in position...

2122
...another worker has joined the party...

2123
...and the weather is somewhat better...

2126
...until, coinciding with Peter and Rose paying a visit, the dumper decides to stop.

2149
Saturday, 2.8.08. By the evening, the new track is looking the part...

2152
...but clearly, there is a way to go!

2171
Sunday, 3.8.08. Trefor and Mike Davies put No. 7 to bed...

2172
...and the new track is looking good...

2174
...and turnout components are laid out but need further work...

2176
...but after a weekend of Teddy Bear trains, the workers are feeling very tired!

2177
With energy to spare, Mike supervises Paul and Trefor as they lay just a couple more lengths of track!


Photographs taken between 21st & 27th July 2008
Taken by David Coleman
Uploaded on 28/07/2008

 

1971
Monday, 21.7.08. Mike Floate has been around, painting walls...

 

1973
...and steelwork...

1974
Tuesday, 22.7.08. ...and helping Trefor dismantle more of Sacradown siding...

1976
...while Richard and Andrew had found more pitch and were heating it up...

1982
...before spreading it thinly over the fabric reinforcement on the Carriage Shed floor.

1988
Meanwhile, Trefor is shunting stock...

1989
...but what makes you think he was cleaning No. 7's tubes earlier?

1994
Thursday, 24.7.08. Mochyn cwl!

1995
Maespoeth yard looks uncannily empty!

1997
The Carriage Shed floor waterproofing has moved on well...

1998
...but the sleepers of Sacradown siding still need removal...

2006
...completed by the evening.

2007
Mike and Trefor are hard at it, clearing stored material to the triangle...

2011
...while Mike has cleared the pit area of building left-overs and Richard and Andrew are heating up more pitch...

2013
...to extend the pit floor waterproofing -

2022
but, the kegs need breaking up to speed melting. Andrew has a rest from the task while Stephanie watches Richard work up a sweat!

2025
Saturday, 26.7.08. The first train is full to capacity - John Trott gives the main talk while others are entertained on the platform.

2026
Andy Cooper has a rest while fettling the pit steel work...

2027
Sunday, 27.7.08. ...and Richard Greenhough changes sleepers in the yard.

2029
The pit waterproofing is nearing completion as Stephanie cleans up.

2030
A good crowd on the first train again.

2031
Dave and John clear a blockage in a coolant supply pipe...

2032
...before Dave and...

2036
...John get back to work on their respective mills, machining parts for Carriage 22.

2037
Malcolm gives the thumbs up as the 12.40 heads up to Corris...

2039
...and then services the air pump while Bob waters No. 7 on their return...

2041
...before oiling round...

2042
...watched by Stephanie, Richard, Helen and Andrew enjoying their lunch.

2043
The 15.00 train's passengers listen intently to John. Any missing Lord's here?

2044
The bucket is well patronised!

2047
Later on, the train is re-formed for No. 7 to haul on the Up...

2051
...for a Birthday party Special.

2053
Andrew drives and...

2054
...Bob fires.

2057
The Birthday Special heads back over Braichgoch Farm crossing...

2058
...before heading back up to Corris following a brief visit to Maespoeth.

2060
Andrew heads No. 7 back towards Maespoeth...

2062
...where Peter and Rosemary call while the train is shunted.

2063
The wiring for the platform lighting has been put in.

2064
Bob tries his hand at driving...

2065
...but Stephanie and Helen look in need of refreshment!

 

Photographs taken between 15th & 20th July 2008
Taken by David Coleman
Uploaded on 21/07/2008

 

1945
Tuesday, 15.7.08. More food for No. 7 has arrived - and gas for the waterproofing of the Carriage Shed - but has anybody got any pitch?

1948
Thursday, 17.7.08. Stan Chatterton demonstrates how to erect shelving for the Carriage Shed, having transported it from Cheshire via. the South Coast!

1949
Saturday, 19.7.08. Andrew smoothes off waterproof mortar to finish the west side wall of the Carriage Shed...

1951
...then helps Trefor adjust the alternator on No. 6...

1952
...before working with Paul and Richard to start dismantling Sacradown siding...

1953
...but all this hard work builds up a thirst!

1954
Meanwhile, Richard Saffrey calls to chat with John Reynard, just as No. 7 makes its appearance...

1955
...and the crew of Mike Floate, Dave Ingram and Dick Kidner exchange banter as they finish their lunch.

1956
Paul grinds off a joint in a pit rail...

1957
...after having made up a much needed new terminal on the welder...

1958
...before balancing precariously to weld more rail to the supporting steel. Let's hope the heat doesn't transfer too well!

1959
After tea break, it is back to work for the Sacradown siding gang...

1960
...but not for long!

1961
The result of their efforts for the day.
 

1962
The 17.10 ex-Corris arrives at Maespoeth, Dave Ingram driving and Mike Floate as fireman. Trefor was also hiding there somewhere!

1963
Sunday, 20.7.08. A coach party arrived for the first train...

1964
...which was driven by Malcolm, on his first morning of duties this year.

1965
The group had a different tour of Maespoeth to the usual, having received a lecture on the railway last night!

1966
The engine crew of Malcolm, Mike and Roger before...

1967
...heading back...

1968
...into Corris.

1969
Y Mochyn has had a change of clothes for the summer!

1970
Adrian (on Control) accepts a down train from Corris.

 

Photographs taken at Amberley on 13th July 2008
Taken by Dave Kingman & Fran Barton
Uploaded on 14/07/2008

 

0001
Dave Kingman is on hand to assist Derek Borrow on the Corris Sales Stand at the Amberley Working Museum Railway Gala Weekend.  

0002
Has Dave sat down and grown a full head of hair ...?

0003
No. It is Fran taking the weight off her feet.


Photographs taken between 8th & 13th July 2008
Taken by David Coleman
Uploaded on 14/07/2008

 

1910
Tuesday, 8.7.08. No. 5 is ticking over...

1911
...as the train in the "loop" siding is made ready...

1912
...coupled up...

1913
...and materials fouling the loading gauge moved...

1916
...to enable waggons on Sacradown siding to be cleared...

1917
...so that No. 6 could gingerly couple up...

1920
...to move the rest of the stock...

1921
...but not before the rails were swept by hand of ballast to smooth its passage (shades of dirty rails on 00 train sets)!

1922
Wednesday, 9.7.08. The result is stock stabled out of the way on the Upper Corris branch siding...

1923
...and all the immediately useful stock in the yard...

1924
...with Sacradown siding clear...

1926
...to enable it to be taken up and re-laid before long with permanent track.

1927
Saturday, 12.7.08. Trefor hunts for tools to enable the diesel locomotives to be serviced in the engine shed...

1929
...and John cuts steel in the hacksaw.

1930
Paul Bailey spaces out rails on the pit rail support beams...

1933
...prior to welding them in position.

1934
Sunday, 13.7.08. Andrew has cleaned up the northern pit in the engine shed...

1935
...and cleans himself up while Richard gives the shed talk to passengers on the last train of the day.

1936
Taking the cue from another pit, fishplates enable the pit to drain!

1938
The last Up train of the day passes Maes y Llan on the approaches to Corris.

 

Photographs taken between 1st & 6th July 2008
Taken by David Coleman
Uploaded on 07/07/2008

 

1850
Stephanie paints more wall and the tar boiler is going...

1851
...while Andrew and Richard set out...

1854
...and drill more holes in the pit rail support steel work.

1856
This enables the last of the pit steel to be erected...

1857
...bolts done up...

1862
...and tea to be drunk...

1863
...until Stephanie hands over the last bolts to complete the assembly.

1864
What makes you think Stephanie has been painting?

1866
Andrew ladles out more molten pitch...

1867
...for Richard to place on the pit floor...

1872
...which adds to the atmosphere inside the Carriage Shed.

1876
Wednesday, 2.7.08. The completed steel work the next day.

1880
Thursday, 3.7.08. A repeat of Tuesday, Stephanie painting...

1882
...Richard waterproofing the pit floor...

1883
...and Andrew cleaning up so that...

1884
...Andrew and Richard can flash over the existing pitch and roll out fabric reinforcement.

1885
Stephanie has just stopped smoking, so finds a job in the roof to sample the fumes from the hot pitch!

1886
Friday, 4.7.08. The state of play next morning - the shed...

1888
...looks a lot brighter (helped by the sun!).

1891
Saturday 5.7.08. A group of members chat while Barry gives the shed talk...

1893
...while Stephanie looks on!

1894
Nigel Bird looks the other way as one of his grand daughters takes photographs!

1895
Andrew adjusts valve gear on the approach to Corris...

1897
...as Stephanie puts the injectors on.

1898
Barry gives a group of passengers on the last train the Shed Talk...

1899
...as a passenger gets serious about his photography.

1900
Making their way back to take seats on the train...

1903
...before the train heads off...

1905
...to Corris, where the Heritage Waggons are on display again.

1906
Dave squeezes past Andrew to undertake reporting duties...

1907
...before riding on the loco as far as Braich Goch Crossing, heading back to Maespoeth...

1908
...and walking on to unlock the wicket gate at Maes-y-Llan...

1909
...before rejoining the last train of the day.


Photographs taken on 29th June 2008
Taken by Richard Greenhough
Uploaded on 05/07/2008

0249
Andy Cooper gives the alternative shed talk, to a group from the Welsh Railways Research Circle, in the carriage shed.

0251
Peter Burberry painted the shed walls.

0252
Phil and Andy bolt up the pit steelwork.

0253
Andy & Phil doing more bolting - and yes, it IS meant to have a curve in the middle!

0254
...while Peter just kept on painting.

0255
Fireman Dave, Driver Dave and Guard Richard Sa....but someone isn't properly dressed...

0256
...that's better ! (Although the Driver will never look as smart as the Guard)

 

 


Photographs taken between 24th & 29th June 2008
Taken by David Coleman
Uploaded on 30/06/2008

 

1787
Tuesday, 24.6.08. Andrew and Richard assemble more pit rail support steel work during the evening...

1788
...in the Carriage Shed...

1789
...while waiting for more pitch to heat up.

1791
It looks like they have been in the Slaters' Arms already...

1792
...despite the care they are taking!

1794
It looks even worse from the other end!

1797
Getting near the end - Richard takes the load as Andrew adjusts a column.

1798
Wednesday, 25.6.08. All assembled - but badly in need of adjustment...

1799
...but a start has been made on the pit floor waterproofing.

1801
Thursday, 26.6.08. They are back to line up the steelwork. A mock-up of the Carriage footboard has been welded to a trolley to test clearances...

1802
...and Stephanie is painting more walls...

1804
...which is all thirsty work.

1805
Stephanie takes a breather while Andrew scoops up molten bitumen...

1806
...to enable Richard to extend the pit waterproofing...

1807
...before returning to break up more bitumen...

1808
...by dropping it onto an angle iron...

1809
...before ladling out more pitch...

1811
...while Stephanie continues with the wall painting.

1815
In case you wonder why the tar boiler is inside, it is persisting down outside...very heavily!

1816
Friday, 27.6.08. The "completed" steel assembly looks better - and yes, the "kink" is deliberate.

1818
The pit waterproofing has been extended.

1819
Saturday, 28.6.08. Trefor is losing his hair, cleaning the frames of No. 7...

1820
...while Dave Quinton adjusts the angle of Carriage No. 21's brake crank...

1821
...Peter Burbery paints the walls in the Carriage Shed...

1823
...Andy adjusts steel work...

1824
...while Paul prepares to weld more rail...

1826
...and later, Richard Saffrey holds up a fence while chatting with Dave Quinton...

1827
...before being chased up a ladder by Bill Newton!

1829
Paul welds more rail after it has been straightened... 

1830
...and you can see why this is necessary!

1831
Sunday, 29.6.08. Richard Greenhough hides in the steps at the south end of the Carriage Shed...

1832
...and more rail is ready for welding in position...

1833
...and Peter is still painting walls...

1835
...some of which are looking quite good!

1837
The sign for the Teddy Bear's weekend has been modified...

1838
...and the station sign has been renewed.

1840
Dave Ingram drives No. 7 for disposal...

1841
...the sign board is in position...

1842
...and Richard, Peter and Dave discuss things at the end of a busy day!


Photographs taken on 21st & 22nd June 2008
Taken by David Coleman
Uploaded on 23/06/2008

 

1743
Saturday, 21.6.08. Wow! Someone has been...

1744
...clearing up in the Engine Shed - to create room to make a permanent connection to the water tank...

1745
...and extended the waterproofing on the Carriage Shed floor...

1746
...as well as set up the gantry to help...

1749
...Andy, Jack and Paul assemble the pit rail support steelwork...

1750
...but there is a snag. Paul 'phones a friend...

1758
...and later all is going well...

1762
...until Andy checks the drawings (again)!

1768
Sunday, 22.6.08. Guard John Wormington greets a family awaiting the 14.40 train ex. - Maespoeth, on the approach road to Braichgoch Farm.

1770
The loco crew consists of Andy, Trefor and Stephanie, who is gaining experience for her DoE Silver Award by gaining a new skill.

1771
Meanwhile, in the Carriage Shed, Paul tacks a rail to the...

1772
...first section of completed pit rail support steel work as Andy checks the measurements.

1776
Andy holds the rail down (and in the right position!) as Paul tacks another weld.

1781
Stephanie and partner Adam receive instructions on gauge glasses from Trefor (in the cab of No. 7), while Andy in a blur cleans up the motion.

1782
The first section of pit steel is assembled and the rest...

1783
...has been set out ready to assemble.

1785
Josh tries his hand, driving No. 6 to put the carriages away after making a practice return trip to Corris.

 

Photographs taken on 14th & 15th June 2008
Taken by David Coleman
Uploaded on 16/06/2008

 

1591
Saturday, 14.6.08. The next section of Carriage Shed floor has been cleared and swept...

1592
...and pit steelwork moved...

1593
...so that the waterproofing can be extended ready for the next section of floor to be screeded...

1594
...requiring edge shuttering to be moved into position while the unpainted sides of steel are handy for cleaning and priming.

1595
Peter Gray cleans up in the pit...

1597
...before starting the clean up of the steel.

1598
While waiting for another batch of pitch to melt, Steve digs the last bit of foundation for the platform retaining wall.

1605
Sunday, 15.6.08. Only a little patch of floor waterproofing left to do for the next section of floor screed...

1606
...and two beams have been painted and three cleaned ready...

1607
...while more of the walls have received a priming coat of paint (in some odd patterns!)...

1608
...and more pots have been filled with concrete on the north platform extension edge wall.

 

Photographs taken on 7th & 10th June 2008
Taken by Dick Kidner
Uploaded on 11/06/2008

 

002
7.6.08. Various shunting took place to give a different train formation for the photographers.

004
No. 7 leading for a change...

005
...with a mixture of heritage stock in the formation...

007
...sprawling to South of the platform.

009
The N.G.R.S. visitors disembark at Corris.

016
10.06.08. We play host for a "school visit".

019
At Maespoeth, Richard Shipman tells them all about the railway.

020
It was a diesel train formation today...

021
...but that did not deter from their enjoyment.


Photographs taken on 7th June 2008
Taken by Meinir Coleman
Uploaded on 11/06/2008

 

0322
Saturday, 7.6.08. John Disley tries No. 9 for size.

0326
Many hands lift the load (from L to R, DC, Richard Shipman, Jack Cooper, John Disley, Malcolm Cameron, Trefor Davies, Andy Cooper, Andrew Rawlins).

0329
DC explains the proposed platform arrangements to John Disley...

 

0330
...while Malcolm chats with Bob and Richard.

   

Photographs taken between 5th & 8th June 2008
Taken by David Coleman
Uploaded on 11/06/2008

 

DSCN1542
Thursday, 5.6.08. Evening activity at the north end of Maespoeth as Trefor moves No. 6...

DSCN1543
...and the 1 in 8 turnout to be laid out for re-gauging...

DSCN1544
...but first, the dunny has to be moved...

DSCN1546
...before the common crossing and stock rails can be off-loaded.

DSCN1547
The remainder of the turnout then has to be re-located...

DSCN1549
...before taking a tea break and reaching for the gnat swatter whi