|

Tuesday, 29.4.08. The sewer vent pipe from the septic tank... |

...has been modified to vent away from the public... |

...and the end of the Carriage Shed floor waterproofing has been largely
completed. |
|

Wednesday, 30.4.08. The track panels have been positioned on the floor
ready for levelling, reinforcement and concrete screed. |

Stock has been moved around Maespoeth yard... |

...and more materials... |
|

...have been delivered for the Carriage Shed. |

With space becoming a premium, these items might not last to 5th
November! |

Friday, 2.5.08. Richard Rugog has supplied a machine... |
|

...to off-load another consignment of rail from Trecwn... |

...which has been delivered to us by Jonathon, here enjoying a cuppa... |

...while his lorry is unloaded. |
|

The consignment mainly consists of turnouts... |

...and fittings, here contained in a timber box. |

Jonathon helps out, loading the machine bucket with point levers... |
|

...and throwing down loose sleepers. |

During the day, coal was delivered for No. 7. |

Plenty of track about - of all sorts of gauges! |
|

A 1 in 8 turnout is already loaded on trolleys for movement to the north
platform extension for laying out and regauging. |

There are plenty more awaiting attention afterwards! |

To fill the trailer, more plain track has been acquired with the
turnouts... |
|

...and with the machine on site, opportunity was taken to dig fill... |

...to fill up the north platform extension. |

Saturday, 3.5.08. Lez has been along to complete another bay of block
work. |
|

Somebody has worked up a good shine on the brass work! |

Andy, Adrian, Paul and Richard scratch heads over how to... |

...re-gauge a turnout. |
|

Bryn and Richard replace sleepers in a turnout... |

...which was not proving easy! |

Sunday, 4.5.08. Y Mochyn has turned football supporter (obviously not
Corris U.F.C.)! |
|

Trefor checks the air pump on No. 7 and the sleepers in the turnout have
been changed successfully. |

Trainee Guard John Wormington checks his train... |

...and the platform extension filling has been roughly levelled. |
|

John Trott supervises Dave Price driving No. 7 up to its train, while
Lez continues block laying. |

Trefor and Richard tamp the replacement sleepers. |

Andrew stops work on re-gauging the turnout as No. 7 eases its train
into Maespoeth while the fill is being levelled and checked for fall. |
|

Steve Harris supervises Andrew and Richard, changing sleepers under the
turnout to be regauged. |

The dumper is being used to move blocks for Lez... |

...and Richard uses the bucket of his machine to slew it onto his
trailer... |
|

...which is narrower than the machine tracks! |

A mixture of names between lorry and machine! |

Not bad for a weekend's work - one regauged turnout awaiting drilling
and spiking... |
|

....as Paul Bailey drives No. 7 on the last working of the day. |

The platform levelling is advancing... |

...ready to receive more turnouts for re-gauging. |
|

Lez has set the edge blocks prior to the last of the waterproofing going
on the west outside wall... |

...and lots of blocks have been moved to keep Lez going! |

One of the track panels has been levelled and packed prior to floor
screeding. |
|

Monday, 5.5.08. John Trott gives his shed talk to a small group of
passengers as the train crew relax... |

...and John Wormington, freshly passed out as Guard, eats his lunch! |

The stock rail supports have been re-welded for the change in gauge. |
|

Lez has laid another bay of concrete blocks... |

...and the mixing point has been moved for the last three bays. |
|