Rheilffordd Corris Railway

Rheilffordd Corris Railway

In the Heart of the Land of the Little Trains

×

  • Home
    • Welcome!
    • Timetable & Special Events
    • Join the Corris Railway Society
    • Renew Existing Membership
    • Other Links
    • Contact Us
  • About Us
    • Introduction
    • Renaissance – 1966 on
    • The Present
    • The Future
      • The Falcon Locomotive
        • Falcon Build Images
      • The Southern Extension
        • Goedwig South
      • Corris Station
    • Volunteering
  • Shop
    • Badges
    • Books & Journals
    • Christmas Cards
    • Drawings & Plans
    • DVD’s
    • Miscellaneous
    • Model Kits
    • Postcards etc.
    • Posters
    • Specials
    • T-Towels
  • More Information
    • Accommodation
    • Maespoeth Engine Shed
    • New Build Carriages
    • Photograph Archives
      • 2020 Photographs
      • 2019 Photographs
      • 2018 Photographs
      • 2017 Photographs
      • 2016 Photographs
      • 2015 Photographs
      • 2014 Photographs
    • Statutory Information
    • The Railway Museum
    • The Tattoo Locomotive
  • News
    • Photographs
    • Videos
    • Press Releases
  • How To Find Us

2020 Photograph Archive

Photographs taken between 8th & 20th September 2020

Tuesday, 8.9.2020. Andy pays a visit to work on carriage No. 23, here joining the others for lunch …
… before resuming work underneath to fit brake pipes – with light …
… while Richard manages without!

Nearby, Tony shows a leg while Charles cuts a waggon transom timber …
… which Bill finishes off …
… until three are completed.

It is then the turn of the longitudinals to have their mortises (roughly) cut out.
Meanwhile, in the Engine Shed Bob is preparing steel for another track jack …
… with the basics of another three prepared.

Wednesday, 9.9.2020. Ooops! This load of tar planings was supposed to have been delivered to Y Felin, Llwyngwern. A good job we have Bro Cader handy to shift them (on a wet day)!
Thursday, 10.9.2020. Tony gives the transoms for the next Heritage Waggon underframes, a coat of preservative …
… while Adrian continues work on the Drop Side Waggon body …

… in many …
… different positions, here (temporarily) on a separate waggon chassis.
Meanwhile, Richard is refining carriage No. 23’s brakes …

… which has by now had its brake pipes fitted, and the underframe painted black.
Sunday, 12.9.2020. Phil and Sam examine the ground frame from Corris, with a view to giving it a thorough overhaul …
… much to Sam’s delight!

Thursday, 17.9.2020. Adrian has continued work on the Drop Side Waggon body, here filling in holes and building up around them as appropriate …
… while Tony has primed the underfloor steel work.
Friday, 18.9.2020. The Oxford household has taken a very important delivery ... (AJO)

Sunday, 20.09.2020. ... and the Editor with "The Corris-Pondent" quarterly newsletter takes over the dining room temporarily. (AJO)

Shopping Cart

What’s New

  • For The First Time Since 1930 Corris Railway Number 4 Will Take Passengers For A Journey From Corris Station
  • Photographs taken on 19th & 25th December 2020
  • Photographs taken between 12th & 18th December 2020
  • Photographs taken between 25th November & 14th December 2020

Latest Photographs

A view of the North platform in the evening light, Christmas now less than a handful of days away, with a new Welsh lockdown due at Midnight tonight this would be the last working day on the railway for a while. The rail bolster wagon sat in the South Platform road, with a bit of work this will be a good addition to the fleet. The first few wagons have reached the North platform, to be propelled back into the South platform to enable space to extract the other few rakes. The fairly poor condition of the CAT carriage here is very noticeable – the chassis seems to look OK. Saturday,  19.12.2020. Time for a grand shunt of the head-shunt at Maespoeth. With the ultimate aim of extracting the “CAT Carriage” for restoration to begin in 2021. Friday 25th December… NadoligLlawen-Happy Christmas, at Corris Station. Chris couples up the CAT wagon (which we had left outside the new wagon shelter mid shunt) in order to propel it towards the new shelter in the hope it would fit. “Doh!” – not quite. With the light failing, loco 6 sits at the head of the ‘serviceable’ works wagons ready to return them to their resting place in the siding. To enable the carriage to thoroughly dry out prior to sorting its contents and begin stripping work, it was dragged into the loco shed behind No.6 and fitted in with a couple of inches to spare. The wagon which until recently was used to store loco 10’s new boiler is next to be dragged out the undergrowth, along with four ex RNAD Trecwn wagons. The view up the siding from the cab of loco 6, the railhead by this point had become extremely greasy and sand needed to be found to gain adhesion.

Latest Products

  • Slate Coaster (matchbox logo) Slate Coaster - Logo design £1.25
  • The Corris Railway by Peter Johnson The Corris Railway: The Story of a Mid-Wales Slate Railway by Peter Johnson £30.00 £25.00
  • Kerr, Stuart & Co Ltd locomotive catalogue Kerr Stuart Locomotive Catalogue Reprint, 2009 £6.95
  • Gala Day Line Up Postcard - Gala Day Line Up £0.50
Falcon Locomotive Appeal LeafletGroup Booking Form
Gift AidStanding Order Form

Rheilffordd Corris Railway

Station Yard Corris, Machynlleth, Powys, SY20 9SH

01654 761701 - Corris Museum & Station
01654 761303 - Maespoeth Engine Shed
General Email - enquiries@corris.co.uk

Rheilffordd Corris Railway Heritage Lottery Funded Transport Trust Heritage Railway Association

Useful Links

  • Corris Discuss Forum
  • Committee Members
  • Data Protection Policy
  • Operational Information
  • Safety Management System

Let’s Get Social

Copyright © 2018-2021 Corris Railway Society All Rights Reserved. Solution by totalwebsystems
  • Facebook
  • Twitter
  • Instagram
  • YouTube
  • TripAdvisor